Weekly Updates

Construction Updates.png

July 10, 2023

Phase one of the Mullan BUILD project is substantially complete.  Some minor activity is planned through July to finish up punch list items, and complete pavement markings on the two roundabouts. Thank you for your patience throughout 2022 and 2023 construction season. This will be the final email update.

 

If you have questions about future trail or roadwork taking place in the area, please reach out to the City of Missoula staff with questions. Contact information for the Public Works Department is linked here. Contact information for Street Maintenance is linked here. Lastly, the City Engineer for Surface Transportations contact information is linked here.

 

Over the coming weeks, if you have additional feedback or questions about the BUILD project please direct questions and feedback to me at becca@bigskypublicrelations.com.

July 3, 2023

Crews are present throughout the Mullan area the week of July 3-7. We anticipate next week's BUILD update to be the final email update for this project.

REMINDERS:

   

Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is substantially completed. Crews are completing seeding and clean-up work in most locations. Final striping work will occur in July in and around the roundabouts. Traffic control will be present. Thank you for your patience and understanding. 

  

---

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Crews have completed bioswales and clean-up work at the north end of Mary Jane Boulevard near Broadway and Flynn Lane.

 

Crews have completed a final seal on the Mary Jane Boulevard and Mullan Road roundabout. Final striping will take place here this week.

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to traffic. Striping has been completed. Permanent road signs have been added, and crews are seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Seeding and final sidewalk/trail work will close out construction in this location. 

 

Crews have completed a final seal on the George Elmer Drive and Mullan Road roundabout. Final striping will take place here this week.

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Fence work has also been completed.

 

OVERALL PROJECT 

Clean-up, signage, bioswales and final concrete work will take place in the coming week as construction comes to a close. Traffic control will be present in the Mullan area, and drivers may experience delays. 

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

June 26, 2023

Crews are present throughout the Mullan area the week of June 26 – 30. 

REMINDERS:

   

Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is substantially completed. Crews are completing seeding and clean-up work in most locations. Final striping work will occur in July in and around the roundabouts. Traffic control will be present. Thank you for your patience and understanding.

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Crews have completed bioswales and clean-up work at the north end of Mary Jane Boulevard near Broadway and Flynn Lane.

 

Over the next two weeks, drivers will notice crews completing a final seal on the Mary Jane Boulevard and Mullan roundabout. Please expect a few minutes of delay.

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to traffic. Striping has been completed. Permanent road signs will be added, and crews will be seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Crews have installed the remaining luminaires. Seeding and final sidewalk/trail work will close out construction in this location. 

 

Over the next two weeks, drivers will notice crews completing a final seal on the George Elmer Drive and Mullan roundabout. Please expect a few minutes of delay.

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Fence work has also been completed.

 

OVERALL PROJECT 

Clean-up, signage, bioswales and final concrete work will take place in the coming weeks as construction comes to a close. Traffic control will be present, and drivers may experience delays. 

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

June 19, 2023

Crews are present the week of June 19 -23 throughout the Mullan area. 

 

REMINDERS:

   

Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is anticipated to be substantially completed mid-June. Final striping work will occur in July in and around the roundabouts. Traffic control will be present. Thank you for your patience and understanding. 

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Crews remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete bioswales and clean-up work. 

 

Over the next two weeks, drivers will notice crews completing a final seal on the Mary Jane Boulevard and Mullan roundabout. Please expect a few minutes of delay.

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to traffic. Striping has been completed. Permanent road signs will be added and crews will be seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Crews have a few remaining luminaires to install. Seeding and final sidewalk/trail work will close out construction in this location. A rectangular rapid flashing beacon (RRFB) will be installed at the trail crossing in this location.

 

Over the next two weeks, drivers will notice crews completing a final seal on the George Elmer Drive and Mullan roundabout. Please expect a few minutes of delay.

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Drivers may notice crews fence work this weekend.

 

OVERALL PROJECT 

Clean up, signage, bioswales and final concrete work will take place in the coming weeks as construction comes to a close. Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March through June, weather dependent.  

 

Crews anticipate this roadwork to be substantially complete by mid-June, weather and material dependent.

 

The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023 and will continue for approximately 10 weeks. More details are included at this link: https://mdt.mt.gov/pubinvolve/oldhwy10/updates.aspx

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

June 12, 2023

Crews are present the week of June 12 -16 throughout the Mullan area. 

REMINDERS:

 

The newly paved England Boulevard extension between Flynn Lane and George Elmer Drive is now OPEN. 

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is anticipated to be substantially completed mid-June. Final striping work will occur in July in and around the roundabouts. Thank you for your patience and understanding. 

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

The closure on Mary Jane Boulevard between Mullan Road and Melrose Place is now lifted. Chip sealing and striping is also finished. Drivers will notice crews finalizing epoxy coating next week.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete bioswales and clean-up work. 

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to traffic.  Striping has been completed. Permanent road signs will be added and crews will be seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Crews have one remaining luminare to install. Seeding and final sidewalk/trail work will close out construction in this location. 

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Drivers may notice crews finalizing shoulder gravel and fence work.

 

OVERALL PROJECT 

Clean up, signage, bioswales and final concrete work will take place in the coming weeks as construction comes to a close. Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March through June, weather dependent.  

 

Crews anticipate this roadwork to be substantially complete by mid-June, weather and material dependent.

 

The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks. More details are included at this link: https://mdt.mt.gov/pubinvolve/oldhwy10/updates.aspx

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

June 5, 2023

Crews are present the week of June 5 – June 9 throughout the Mullan area. 

 

REMINDERS:

 

The newly paved England Boulevard extension between Flynn Lane and George Elmer Drive is now OPEN. 

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is anticipated to be fully completed mid-June. Thank you for your patience and understanding. 

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Seeding for landscaping in the roundabout medians is completed. Due to rain, the closure mentioned last week is pushed out.  There will be a brief closure on Mary Jane Boulevard between Mullan Road and Melrose Place through June 7. Detour routes will be indicated with signs. Lastly, next week, final chip sealing will take place on Mullan Road surrounding the Mary Jane Boulevard/Mullan Road roundabout. Due to materials used to chip seal, drivers may experience 10 – 20- minute delays traveling through this area.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete bioswales. 

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to drivers. Permanent road signs will be added and crews will be seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Luminaires installation is finishing up this week. Landscaping, ditch and curb will finish up work in this area. In addition, chip sealing and sidewalks will be completed in the next week or so. Median concrete and removal of the detour can also be expected.

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Drivers may notice crews finalizing shoulder dirt and fence work.

 

OVERALL PROJECT 

Striping will take place throughout the project area in the coming weeks. Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Crews anticipate this roadwork to be complete mid-June, weather and material dependent.

 

The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks. More details are included at this link: https://mdt.mt.gov/pubinvolve/oldhwy10/updates.aspx

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

Please send direct questions and feedback to me at becca@bigskypublicrelations.com.

May 30, 2023

Crews are present the week of May 30 – June 2 throughout the Mullan area. 

 

REMINDERS:

 

The newly paved England Boulevard extension between Flynn Lane and George Elmer Drive is now OPEN. 

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is anticipated to be fully completed by early June. Thank you for your patience and understanding. 

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Seeding for landscaping in the roundabout medians is completed. Trails will be paved at the end of May. There will be a brief closure on Mary Jane Boulevard between Mullan Road and Melrose Place from May 30 – June 2. Detour routes will be indicated with signs. Lastly, next week, final chip sealing will take place on Mullan Road surrounding the Mary Jane Boulevard/Mullan Road roundabout. Due to materials used to chip seal, drivers may experience 10 – 20- minutes delays traveling through this area.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete seeding. Paving is complete in this location.

 

ENGLAND BOULEVARD

England Boulevard between Flynn Lane and George Elmer Drive is open to drivers. Temporary road signs will be added and crews will be seeding the sides of the roadway. 

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Luminaires installation continues this week. Paving in this area is complete. Landscaping, ditch and curb will finish up work in this area. In addition chip sealing, median pours and sidewalks will be completed. 10-20- minute delays are to be anticipated when traveling through this area. 

 

FLYNN LANE

Work is complete at the Flynn Lane and Mullan Road intersection. Drivers may notice crews finalizing shoulder dirt and fence work.

 

OVERALL PROJECT 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Crews anticipate this roadwork to be complete by the first week of June, weather and material dependent.

 

The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks. More details are included at this link: https://mdt.mt.gov/pubinvolve/oldhwy10/updates.aspx

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com.

May 22, 2023

Throughout the Mullan area, crews will be present the week of May 22 - 26. Kiewit and contractors will not be present on Monday, May 29, Memorial Day.

 

REMINDERS:

 

The newly paved England Boulevard extension between Flynn Lane and George Elmer Drive is CLOSED. Though paving is complete, the final painting and shoulder must be completed. This roadway will open for Memorial Day weekend. 

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

All roadwork is anticipated to be fully completed by early June. Thank you for your patience and understanding. 

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Seeding for landscaping in the roundabout medians will take place this week. Trails will be paved at the end of May. There will be a brief closure on Mary Jane Boulevard between Mullan Road and Melrose Place from May 30 – June 2. Detour routes will be indicated with signs.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane to complete seeding and striping. Trails will be paved at the end of May. 

 

ENGLAND BOULEVARD

The paving is complete on England Boulevard. This week, striping and seeding will occur. Beginning Friday, May 26 (Memorial Day weekend), England Boulevard between Flynn Lane and George Elmer Drive will be open to drivers.

 

GEORGE ELMER DRIVE

The bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Paving in this area is complete. Curb and Median work will start this week, and continue into next. Luminaires installation continues this week. Landscaping, drainage improvements and curb will finish up work in this area.

 

FLYNN LANE

Work is completed at the Flynn Lane and Mullan Road intersection. Drivers may notice crews finalizing shoulder dirt work.

 

OVERALL PROJECT 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Crews anticipate completing this roadwork by the first week of June, weather and material dependent.

 

The Montana Department of Transportation is conducting pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

May 15, 2023

Crews are present the week of May 15 – 19 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Roadwork is anticipated to be completed by early June. Thank you for your patience and understanding. 

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Seeding for landscaping in the roundabout medians will take place in the middle of May. Trails will be paved at the end of May. There will be a brief closure on Mary Jane Boulevard between Mullan Road and Melrose Place from May 30 – June 2. Detour routes will be indicated with signs.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, completing sewer work. Trails will be paved at the end of May. Crews will soon be seeding and striping in this area.

 

ENGLAND BOULEVARD

Paving is complete on England Boulevard. This week, striping and seeding will occur. In late May, England Boulevard between Flynn Lane and George Elmer Drive will be open to drivers.

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Luminaires installation continues this week. Paving in this area is almost complete. Landscaping, ditch and curb will finish up work in this area.

 

FLYNN LANE

Flynn Lane will be closed at the Mullan Road and Flynn Lane intersection from May 15 – May 19 in order to reconstruct the intersection.Hellgate School and all residents located in this area will have access to their properties. Drivers will be directed to use Mary Jane Boulevard to access Mullan Road and directed through Chelsea Drive and England Boulevard to connect to Flynn Lane.

 

A detour map is included for your reference. 

 

OVERALL PROJECT 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Crews anticipate completion of this roadwork by the first week of June, weather and material dependent.

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work began in mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods. In addition, the Montana Department of Transportation will conduct pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

May 8, 2023

Crews are present the week of May 8 - 12 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

Crews have completed the majority of concrete work in this location and are now completing the remaining sidewalk pours. Seeding for landscaping in the roundabout medians will take place in the middle of May. Decorative concrete pouring in the center of the roundabout medians is also almost complete.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, completing utility work, trails and ADA sidewalks. Crews will soon be seeding and striping in this area.

 

ENGLAND BOULEVARD

Paving will begin on England Boulevard in mid-May. Following that, 3-4 days of paving, striping and seeding will occur. Shortly thereafter, in late May, England Boulevard between Flynn Lane and George Elmer Drive will be open to drivers.

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Luminaires installation continues this week. Paving in this area will begin May 8. During paving, drivers traveling east will be directed to use the frontage road instead of the southern side of the roundabout through May 10.

 

During this time, crews will be completing the following work:

• Milling out the temporary asphalt on Mullan Road.

• Paving the final asphalt lift (top surface).

• Finishing roundabout curbs.

• Roundabout landscaping.

 

Following this closure, landscaping will finish up work in this area.

 

FLYNN LANE

Flynn Lane will be closed between Chelsea Drive and Mullan Road from May 15 – May 19 for pothole filling and striping. Hellgate School and all residents located in this area will have access to their properties. During this time, drivers will be directed to use Chelsea Drive and England Boulevard to connect to Mary Jane Boulevard for detours around this street closure. 

 

A detour map is included for your reference. 

 

OVERALL PROJECT 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Crews anticipate completion of this roadwork by the first week of June, weather and material dependent.

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods. In addition, the Montana Department of Transportation will conduct pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023, and will continue for approximately 10 weeks.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

May 1, 2023

Crews are present the week of May 1 - 5 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE:

 

MARY JANE BOULEVARD

The week of May 1 - 5, construction crews remain near the Mary Jane Boulevard and Mullan Road roundabout. Crews have completed the majority of concrete work in this location and are now completing final sidewalk pours. Seeding for landscaping in the roundabout medians will take place in the middle of May.

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, completing utility work and prepping for trails and ADA sidewalks. Crews will be striping in this area.

 

ENGLAND BOULEVARD

Crews have completed dry wells and curb on the future England Boulevard connection. Paving will begin in a few weeks. Updates will be provided as this work approaches. Lines will be painted mid-May. 

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Luminaires installation will start this week. Paving in this area will begin May 8.  During paving, drivers traveling east will be directed to use the frontage road instead of the southern side of the roundabout through May 10.

 

During this time, crews will be completing the following work:

 

• Milling out the temporary asphalt on Mullan Road.

• Paving the final asphalt lift (top surface).

• Finishing roundabout curbs.

 

FLYNN LANE

On May 5, the northbound driving lane on Flynn Lane from England Boulevard to Camden Street will be detoured. 

 

Flynn Lane will be closed between Chelsea Drive and Mullan Road from May 15 – May 19 for pothole filling and striping on Flynn Lane and Mullan Road in this area. Hellgate School and all residents located in this area will have access to their properties. During this time, drivers will be directed to use Chelsea Drive and England Boulevard to connect to Mary Jane Boulevard for detours around this street closure.

 

OVERALL PROJECT

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods. In addition, the Montana Department of Transportation will conduct pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction began on April 24, 2023 and will continue for approximately 10 weeks.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

April 24, 2023

Crews are present the week of April 24 - 28 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

The week of April 24 - 28, construction crews remain near the Mary Jane Boulevard and Mullan Road roundabout. Crews are completing final concrete work in the roundabout medians and sidewalk. Luminaire poles have been placed, and lighting is now present as of Friday, April 14. 

 

Crews also remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, completing utility work and prepping for trails and ADA sidewalks. 

 

ENGLAND BOULEVARD

Crews have completed dry wells and curb on the future England Boulevard connection. Paving will take place starting May 1, weather permitting. 

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road.

 

Starting Monday, April 24, crews will be milling on Mullan Road in the Mary Jane Boulevard roundabout. Paving will begin here on May 1. Drivers traveling east will be directed to use the frontage road instead of the southern side of the roundabout through May 3.

 

During this time, crews will be completing the following work:

• Fixing curb on the south side of the George Elmer Drive roundabout.

• Milling out the temporary asphalt on Mullan Road.

• Paving the final asphalt.

• Finishing roundabout curbs.

 

FLYNN LANE

On May 5, the northbound Flynn Lane from England Boulevard to Camden Street will be detoured. 

 

Flynn Lane will be closed between Chelsea Drive and Mullan Road from May 15 – May 19. Hellgate School and all residents located in this area will have access to their properties.

 

During this time, drivers will be directed to use Chelsea Drive and England Boulevard to connect to Mary Jane Boulevard as a detour to Mullan Road and Reserve Street.

 

Crews are filling in potholes and line painting at Flynn Lane and Mullan during this time.

 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods. In addition, the Montana Department of Transportation will conduct pavement preservation operations on West Broadway, also known as Old Hwy 10 (US 10), from the intersection of West Broadway and US Highway 93 (US 93), near Love’s Truck Stop to the Reserve Street overpass, north of Costco. Construction will begin April 24, 2023, and continue for approximately 10 weeks.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

April 10, 2023

Crews are present the week of April 17 -21 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

During the week of April 17 – 21, construction crews remain near the Mary Jane Boulevard and Mullan Road roundabout. Luminaire poles have been placed and lighting is now present as of Friday, April 14. Concrete median work and sidewalk will occur on the Mullan/Mary Jane Boulevard roundabout. 

 

Crews remain at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, prepping for trails and sidewalks. 

 

ENGLAND BOULEVARD

Crews continue working on the future England Boulevard connection, completing the curb and gutter. Much of the curb and gutter work has been completed on England Boulevard. The contractors will focus on finishing the base course to prepare for paving the first week of May. A few photos of this work are attached.

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Lighting will be added at this roundabout as well. A crosswalk will be added across Mullan Road at the George Elmer Drive Roundabout this spring. This will help slow traffic traveling east and west on Mullan Road to allow non-motorized safer passage across the busy road.

 

 OTHER

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com

April 10, 2023

Crews are present the week of April 10 - 14 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

MARY JANE BOULEVARD

The week of April 10 - 14, construction crews remain near the Mary Jane Boulevard and Mullan Road roundabout. Luminaire poles will be placed, and slope and concrete work will occur on the Mullan/Mary Jane Boulevard roundabout. 

 

Crews will also be present at the north end of Mary Jane Boulevard near Broadway and Flynn Lane, completing utility work, and prepping for trails and sidewalks. 

 

ENGLAND BOULEVARD

Crews continue working on the future England Boulevard connection, completing bioswales and curb and gutter. Much of the curb and gutter work has been completed on the north side of the roadway connection. The contractors will focus on pouring the south side curb and gutter in the coming weeks.

 

GEORGE ELMER DRIVE

Bike path and final roundabout work are taking place on the south end of George Elmer Drive near Mullan Road. Lighting will be added at this roundabout as well. A crosswalk will be added across Mullan Road at the George Elmer Drive Roundabout this spring. This will help slow traffic traveling east and west on Mullan Road to allow non-motorized safer passage across the busy road.

 

Traffic control will be present, and drivers may experience delays. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present, and drivers will likely be limited to one lane for certain periods.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

April 3, 2023

Crews are present the week of April 3 - 7 throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol is present to monitor the construction area. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

The week of April 3 - 7, construction crews will be working near the Mary Jane Boulevard and Mullan Road roundabout. Sidewalks, pedestrian path and median work will take place this week. Crews have removed the south end of the roundabout detour.  Lighting on the roundabouts will be installed in early April. Traffic control will be present and drivers may experience delays.

 

Crews continue working on the future England Boulevard connection, completing bioswales and curb and gutter.

 

In addition, bike path and final roundabout work will be taking place on the south end of George Elmer Drive near Mullan Road. This spring, a crosswalk will be added across Mullan Road at the George Elmer Drive Roundabout. This will help slow traffic traveling east and west on Mullan Road.

 

Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

The Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present and drivers will likely be limited to one lane for certain time periods.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com

March 27, 2023

The week of March 27 -31 crews are present throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway Patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

The week of March 27 – 31, drivers will continue to see crews near Mary Jane Boulevard and Mullan Road roundabout. Crews will be installing lighting and median concrete this week. Lighting on the roundabouts will be installed in early April. Traffic control will be present and drivers may experience minor delays.

 

In the coming weeks, crews will also be present on the future England Boulevard connection completing bioswales and curb and gutter. In addition, bike path and final roundabout work will be taking place on the south end of George Elmer Drive near Mullan Road.

 

Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

In addition, the Montana Department of Transportation, Broadway and Mary Jane Boulevard intersection signal work will begin mid-April and will be wrapped up this summer, weather permitting. There will be no road closures/detours throughout construction. However, traffic control will be present and drivers will likely be limited to one lane for certain time periods.

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to Becca at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

March 20, 2023

The week of March 20 -24, crews are present throughout the Mullan area. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN THROUGHOUT THE WORK ZONE. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

  

---

 

CONSTRUCTION UPDATE

 

Missoula County, in partnership with the City of Missoula, resumed construction on the Mullan BUILD project the week of March 13. Roadwork will take place from March through June, weather permitting.

 

The week of March 20 – 24, drivers will continue to see crews near the Mary Jane Boulevard and Mullan Road roundabout. Crews will be removing the detour on the south end of the roundabout and begin work on sidewalks and bike lanes in this area. Drivers may experience minor delays.

 

In the coming weeks, crews will be completing utility work on the future England Boulevard connection in addition to work on the south end of George Elmer Drive near Mullan Road.

 

Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

This spring and summer, Missoulians can anticipate construction occurring on Mary Jane Boulevard, George Elmer Drive and England Boulevard, as these are the initial priorities of the BUILD project. 

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

March 13, 2023

Missoula County, in partnership with the City of Missoula, will resume construction on the Mullan BUILD project the week of March 13. Roadwork will take place from March through June, weather permitting.

 

In 2022, crews completed work on the northern and southern portions of Mary Jane Boulevard. In addition, crews added two roundabouts to Mullan Road at the intersections of George Elmer Drive and Mary Jane Boulevard. They also completed improvements at the north end of George Elmer Drive where the street will intersect with England Boulevard.  

 

Starting in the spring of 2023, BUILD project team members will return to complete the final touches on these roadways, such as sidewalk and bike lane installation, trail construction, lighting, chip sealing andpavement markings. Crews will also complete the street extension of England Boulevard that will connect Flynn Lane and George Elmer Drive.

 

Specifically, the week of March 13, crews will be present around the roundabout at Mary Jane Boulevard and Mullan Road. Drivers will not be impacted as crews will be off the roadway. 

 

In addition, Kiewit Corporation, the project’s contractor, will begin roadwork on the England Boulevard connection this March. Drivers will also notice utility work and roundabout lighting installation beginning along Mullan Road. Delays of up to 10 to 15 minutes can be anticipated when traveling throughout the project area from March to June, weather dependent.  

 

Please remember to SLOW DOWN in the work zone and be mindful of workers, nearby students and other cars.

 

Updates will be provided regularly on construction progress and anticipated delays. 

 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of the Mullan BUILD project construction. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses. The BUILD project will ultimately play an integral role in how Missoula grows.

 

Please send direct questions and feedback to me at becca@bigskypublicrelations.com. Visit the project web page for more details regarding the Mullan BUILD project: https://www.mullanbuild.com

January 23, 2023

CONSTRUCTION UPDATE:

All major roadwork remains paused for the winter. Weather permitting, construction in the Mullan area (Mary Jane Boulevard, George Elmer Drive, England Boulevard) will resume in the spring of 2023.

 

In the meantime, drivers may see permanent signage in the area being updated or replaced.

 

In addition, lighting fixtures for the George Elmer Drive/Mullan Road and Mary Jane Boulevard/Mullan Road roundabouts are anticipated to be installed this February, weather permitting.

 

Construction details will continue to be communicated as spring approaches.

 

General Updates

Mullan Road's two roundabouts are nearly complete, with landscaping, approach work, and splitter island work still to be completed.

 

Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project. Final work on this phase will take place in 2023. This includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

November 21, 2022

From November 21 through November 25, crews will wrap up work on the Mullan BUILD Project for the year. On behalf of the BUILD project team, we wish you a happy and safe Thanksgiving week!

 

REMINDERS:

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

CONSTRUCTION UPDATE:  

 

Mary Jane Boulevard North

Mary Jane North project improvements are complete for this construction season.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are installing a signal at the intersection of Mary Jane Boulevard and West Broadway, weather permitting. The MDT project also includes improvements at the intersection of Flynn and West Broadway, requiring traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. Questions? Please contact mredmond@mt.gov.

 

Mary Jane Boulevard South & Roundabout

Traffic is now entirely on the roundabout. The roundabout is fully open and Mary Jane Boulevard provides a connection to Broadway Street. As weather permits, crews will continue working outside the curb and gutter and installing initial lighting facilities. Due to streetlight lead times, streetlights will be installed in January of 2023. In the meantime, additional signs and delineators have been added to promote safety. 

 

George Elmer Drive & Roundabout

Crews paved the first lift for the eastbound traffic, and the second lift will be paved in the spring of 2023. Crews have also paved Marie Drive and completed the frontage road. The George Elmer Drive roundabout is now fully open in its winter configuration. George Elmer Drive between Pius Way and Abby Lane is also planned to open soon. 

 

England Boulevard

Shaping and grading the existing ground will continue next year, along with installation of curb, gutter, and paving. Due to cold weather and snow, the roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane will be paused in the coming weeks and picked up again in 2023.

 

General Updates 

As mentioned above, Mullan Road's two roundabouts are almost fully completed!  The lighting, sidewalks, landscaping, and RRFB’s at both roundabouts still need to be installed, and some paving, curb pours, and median islands remain on the George Elmer roundabout.  While some improvements are still to come, the roundabouts are fully operational at this point.

 

Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. Please also look for and yield to pedestrians and bicyclists at crosswalks prior to entering and exiting the roundabouts.

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which has been substantially completed by the end of 2022. The work included utility infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

November 14, 2022

The week of November 14 through November 18, crews remain throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for being so understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

CONSTRUCTION UPDATE:  

 

Mary Jane Boulevard North

Most of the Mary Jane North project improvements are complete for this construction season. The remaining scope will be focused on the back side of the curb and gutter to ensure proper drainage this winter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are installing a signal at the intersection of Mary Jane Boulevard and West Broadway, weather permitting. The MDT project also includes improvements at the intersection of Flynn and West Broadway, requiring traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. Questions? Please contact mredmond@mt.gov.

 

Mary Jane Boulevard South & Roundabout

Traffic is now entirely on the roundabout. As weather permits, crews will continue working outside curb and gutter and start installing initial lighting facilities. Weather permitting, the roundabout is expected to be fully open on Tuesday, November 15, allowing access north along Mary Jane Boulevard.

 

George Elmer Drive & Roundabout

Crews paved the first lift for the eastbound traffic, and the second lift will be paved in the spring of 2023. Crews have also paved Marie Drive and completed the frontage road. The George Elmer Drive roundabout is now fully open in its winter configuration. George Elmer Drive between Pius Way and Abby Lane is also planned to open soon.

 

England Boulevard

Shaping and grading of the existing ground continue, along with geotextile and subgrade material placement. Due to incoming cold weather and snow, the roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane will be paused in the coming weeks and picked up again in 2023.

 

General Updates

As mentioned above, Mullan Road's two roundabouts are nearing completion! 

 

Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

November 7, 2022

The week of November 7 through November 11, crews remain throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for being so understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

CONSTRUCTION UPDATE:

  

Mary Jane Boulevard North

Most of the Mary Jane North project improvements are complete for this construction season. The remaining scope will be focused on the back side of the curb and gutter to ensure proper drainage this winter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are working on the installation of a signal at the intersection of Mary Jane Boulevard and West Broadway, weather permitting. The MDT project also includes improvements at the intersection of Flynn and West Broadway, requiring traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. Questions? Please contact mredmond@mt.gov.

 

Mary Jane Boulevard South & Roundabout

Traffic is now entirely on the roundabout. As weather permits, crews will continue working outside curb and gutter and start installing initial lighting facilities. Weather permitting, the roundabout is expected to be fully open on Monday, November 14, allowing access north along Mary Jane Boulevard.

 

George Elmer Drive & Roundabout

Crews paved the first lift for the eastbound traffic, and the second lift will be paved in the spring of 2023. The roundabout is now open to eastbound and westbound Mullan traffic. Crews have paved Marie Drive and completed the frontage road. The George Elmer Drive roundabout will be fully opened in its winter configuration by Monday, November 7. George Elmer Drive between Pius Way and Abby Lane is also planned to open soon.

 

England Boulevard

Shaping and grading of the existing ground continues, along with geotextile and subgrade material placement. Due to incoming cold weather and snow, the roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane will be paused in the coming weeks and picked up again in 2023.

 

General Updates

As mentioned above, Mullan Road's two roundabouts are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, use your turn signal to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

October 31, 2022

The week of October 31 through November 4, crews remain throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for being so understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

CONSTRUCTION UPDATE:

  

 

Mary Jane Boulevard North

Most of the Mary Jane North project improvements are complete for this construction season. The remaining scope will be focused on the back side of the curb and gutter to ensure proper drainage this winter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are working on the installation of a signal at the intersection of Mary Jane Boulevard and West Broadway. The MDT project also includes improvements at the intersection of Flynn and West Broadway, requiring traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. 

 

Mary Jane Boulevard South & Roundabout

Traffic is now entirely on the roundabout. As weather permits, crews will pave the access road south of the roundabout and will be completing median work. The roundabout and access to Mary Jane Boulevard will be complete and fully opened to traffic later this fall.

 

George Elmer Drive & Roundabout

Crews paved a temporary lane for eastbound traffic. The roundabout is now open to eastbound and westbound Mullan traffic. Crews will be focusing on paving Marie Drive early this week and completing the frontage road. 

 

Final paving is expected to take place in mid-November. During paving operations, the Mullan Road and George Elmer Drive intersection will be limited to one lane and flaggers will be present to direct traffic. Updates will continue to be provided as the potential paving date approaches. The George Elmer Drive roundabout will be fully opened to traffic throughout the winter.

 

England Boulevard

Shaping and grading of the existing ground continues, along with geotextile and subgrade material placement. Depending on weather and other factors, the roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane may be completed as soon as this fall.  If England Boulevard is complete this fall, it will be open to traffic this winter.

 

General Updates

As mentioned above, Mullan Road's two roundabouts are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

October 24, 2022

The week of October 24 through 28, crews remain throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for being so understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

CONSTRUCTION UPDATE:

  

Mary Jane Boulevard North

Most of the Mary Jane North project improvements are complete for this construction season. The remaining scope will be focused on the back side of the curb and gutter to ensure proper drainage this winter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are working on the installation of a signal at the intersection of Mary Jane Boulevard and West Broadway. The MDT project also includes improvements at the intersection of Flynn and West Broadway, requiring traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. 

 

Mary Jane Boulevard South & Roundabout

Line work has been completed, and traffic is now entirely on the roundabout. As weather permits, crews will pave the access road south of the roundabout and continue curb and gutter work within the medians of the roundabout. The roundabout and access to Mary Jane will be complete and fully opened to traffic later this fall.

 

George Elmer Drive & Roundabout

Crews paved a temporary lane for eastbound traffic. The roundabout is now open to eastbound and westbound Mullan traffic. Crews will be focusing on reconstructing Marie Drive and completing the frontage road. Remaining paving operations at the roundabout will be completed as weather permits.  

 

England Boulevard

Shaping and grading of the existing ground have now begun, along with geotextile and subgrade material placement. Depending on weather and other factors, the roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane may be completed as soon as this fall.  If England Boulevard is complete this fall, it will be open to traffic this winter.

 

General Updates

As mentioned above, Mullan Road's two roundabouts are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exiting, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

October 17, 2022

The week of October 17 through 24, crews remain present throughout the Mullan area, including on weekends. Thank you for your continued patience as 2022 construction nears a close. 

 

REMINDERS:

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROADHighway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway or England and Reserve to travel east. 

 

---

 

CONSTRUCTION UPDATE:

   

Mary Jane Boulevard North

A majority of the Mary Jane North project improvements are complete for this construction season.  The remaining scope will be focused on the back side of the curb and gutter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are working on the installation of a signal at the intersection of Mary Jane Boulevard and West Broadway. The MDT project also includes improvements at the intersection of Flynn and West Broadway, which will require traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. 

 

Mary Jane Boulevard South & Roundabout

The detour was removed on Mullan Road and all traffic is on the roundabout. In addition, work continues north of the roundabout. The roundabout and access to Mary Jane will be complete this fall, and the roadway will be fully opened to traffic later this fall.

George Elmer Drive & Roundabout

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. The first phase of paving has been completed. This week, drivers will be directed to use the westbound lanes of the roundabout while paving takes place on the eastbound lanes and the access road south of the roundabout. In the coming weeks, as work is completed in this area, the roundabout will be fully opened, and the frontage road detours will be removed.  George Elmer will be fully opened to traffic later this fall after completion of necessary activities.

 

England Boulevard

Shaping and grading of the existing ground has now begun, along with the placement of geotextile and subgrade material. This is in preparation for curb and gutter work. The roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane may be completed as soon as this fall depending on weather and other factors.  If England Boulevard is complete this fall, it will be open to traffic this winter.

 

General Updates

As just mentioned above, the two roundabouts on Mullan Road are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exit, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

 

Take care,

Becca MacLean, on behalf of the BUILD Project Team

October 10, 2022

The week of October 10 through 17, crews remain present throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway or England and Reserve to travel east. 

 

---

 

CONSTRUCTION UPDATE:

  

Mary Jane Boulevard North

A majority of the Mary Jane North project improvements are complete for this construction season.  The remaining scope will be focused on the back side of the curb and gutter.

 

The Montana Department of Transportation (MDT) has a separate project on West Broadway, and crews are working on the installation of a signal at the intersection of Mary Jane Boulevard and West Broadway. The MDT project also includes improvements at the intersection of Flynn and West Broadway, which will require traffic control along West Broadway.  Please follow traffic sign information for detours and local access. Please drive the posted speed limit and watch for workers and equipment near the roadway. 

 

Mary Jane Boulevard South & Roundabout

A detour remains on Mullan Road located immediately east of Flynn Lane. This Saturday 10/08, crews completed line painting in the roundabout and eastbound traffic was shifted onto the roundabout. This traffic shift is allowing crews to prepare for paving the access road south of the roundabout.  The roundabout and access to Mary Jane will be complete this fall, and the roadway will be fully opened to traffic later this fall.

 

George Elmer Drive & Roundabout

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. The first phase of paving was completed last week. Soon, drivers will be directed to use the westbound lanes of the roundabout. In the coming month, as work is completed in this area, the roundabout will be fully opened, and the frontage road detours will be removed.  George Elmer will be fully opened to traffic later this fall after completion of necessary activities.

 

England Boulevard

Crews were able to complete the final activities for the installation of sumps, water infrastructure, and sewer infrastructure last week.  Testing of the water system is forthcoming.

 

Shaping and grading of the existing ground has now begun, along with the placement of geotextile and subgrade material. The roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane may be completed as soon as this fall depending on weather and other factors.  If England Boulevard is complete this fall, it will be open to traffic this winter.

 

General Updates

As just mentioned above, the two roundabouts on Mullan Road are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exit, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

October 3, 2022

The week of October 3-7, crews remain present throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway or England and Reserve to travel east. 

 

---

 

CONSTRUCTION UPDATE:

  

Major roadwork has wrapped up at the north end of Mary Jane Boulevard. Striping has been completed.  

 

Connected to this, but part of a different MDT project, crews are working on the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. The MDT project also includes improvements at the intersection of Flynn and Broadway, which will require traffic control along Broadway.

 

The Flynn Lane and Broadway intersection is closed. Drivers can use Mary Jane Boulevard to access Broadway.

 

In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. The westbound traffic has been shifted onto the roundabout, and eastbound traffic will be on the detour for one or two more weeks. Here, crews are continuing paving of the roundabout and utility work at the intersection of Mary Jane Boulevard and Mullan Road. 

 

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly constructed frontage road. George Elmer roundabout concrete paving will take place this week.

 

The two roundabouts on Mullan Road are nearing completion! Roundabouts move traffic efficiently. As a reminder, please slow down, yield, and look left when approaching the roundabout. Drivers within the roundabout have the right of way. Once clear, enter the roundabout. Prior to exit, put your blinker on to indicate to other drivers where you intend to exit the roundabout. The idea is that movement occurs continually through the roundabout to keep traffic flowing. 

 

Similar to past weeks, utility and water work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. Sewer and water improvements along England Boulevard are scheduled to be complete by mid-October.  The roadway improvements along England Boulevard between George Elmer Drive and Flynn Lane may be completed as soon as this fall depending on weather and other factors.  If England Boulevard is complete this fall, it will be open to traffic this winter.

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

September 26, 2022

The week of September 26-30, crews remain present throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway or England and Reserve to travel east. 

 

---

 

CONSTRUCTION UPDATE:

 

Various traffic changes are taking place in the coming weeks. These locations are bolded below.

 

Major roadwork has wrapped up at the north end of Mary Jane Boulevard. Striping has been completed.  

 

Connected to this, but part of a different MDT project, crews are working on the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway.

 

The Flynn and Broadway intersection continues to be closed. Work is estimated to be completed by the end of the week. All businesses on this stretch of Flynn Lane will be accessible. Traffic will be directed to use Mary Jane Boulevard to access Broadway.

 

In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. The westbound traffic has been shifted onto the roundabout, and eastbound traffic will be on the detour for a few more weeks. Here, crews are continuing paving of the roundabout and utility work at the intersection of Mary Jane Boulevard and Mullan Road. 

 

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly construction frontage road. George Elmer South curb work is progressing as fast as possible along with all roundabout concrete work to prep for paving. 

 

The the intersection of England Boulevard and Flynn Lane is back open, following work concluding on Friday. Crews completed water main and intersection improvement work. 

 

Similar to past weeks, utility and water work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Mark your calendars: A second construction open house is scheduled on Tuesday, September 27 from 4:30pm – 6:30pm at the Hellgate Elementary School Cafeteria in Building 3. The project team will be present to answer questions. No formal presentation will be made. Please join us to ask questions and learn more.

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

 

September 19, 2022

The week of September 19 through September 23, crews remain present throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway or England and Reserve to travel east. 

 

---

 

CONSTRUCTION UPDATE:

 

Various traffic changes are taking place in the coming weeks. These locations are bolded below.

Major roadwork has wrapped up at the north end of Mary Jane Boulevard. Striping has been completed.  

 

Connected to this, but part of a different MDT project, crews are working on the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway.

 

This MDT project also includes improvements to the Flynn Lane/Broadway intersection. The Flynn and Broadway intersection will be closed starting the week of Monday, September 19. This closure will be present for 2-3 weeks. All businesses on this stretch of Flynn Lane will be accessible. Traffic will be directed to use Mary Jane Boulevard to access Broadway.

 

In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. The west bound detour will be shifted onto the roundabout on Monday, September 19. Here, crews are continuing paving of the roundabout and utility work at the intersection of Mary Jane Boulevard and Mullan Road. 

 

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly constructed frontage road. 

 

Starting Monday, September 19, a closure will be present at the intersection of England Boulevard and Flynn Lane. Detour signs will direct traffic to alternate routes. The closure will take place for 3 – 5 days as water main and intersection improvement work is completed. A photo of the closure and detour route (including the MDT Flynn and Broadway closure) is below.

 

Similar to past weeks, utility and water work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. 

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

Mark your calendars: A second construction open house is scheduled on Tuesday, September 27 from 4:30pm – 6:30pm at the Hellgate Elementary School Cafeteria in Building 3. The project team will be present to answer questions. No formal presentation will be made. Please join us to ask questions and learn more.

Open House on September 27

The City of Missoula and Missoula County invite you to attend an open house discussing construction and traffic control details for the Mullan BUILD project in Missoula. 

 

On Tuesday, September 27, the Mullan BUILD team will host an open house at the Hellgate Elementary School Cafeteria, Building 3 on Flynn Lane from 4:30 p.m. to 6:30 p.m. No formal presentation will be made. Project team members will be present to answer questions about the construction schedule, roundabout designs on Mullan Road, multi-modal transportation elements, surrounding area projects and more. 

 

The goal of the Mullan BUILD project is to support residential and commercial development while also honoring and being sensitive to the surrounding environment. Select roadway and subsurface construction is in progress on Mary Jane Boulevard, Flynn Lane, George Elmer Drive, Mullan Road and England Boulevard. For a breakdown of the project schedule, please visit the webpage linked here.

 

Missoula County and the City of Missoula received a $13 million federal BUILD grant to construct a new road network in the Mullan area. This isn’t enough to fund the entire infrastructure system, which is estimated to be a $40 million project. As such, Mary Jane Boulevard South; Mary Jane Boulevard North; George Elmer Drive; and England Boulevard will be constructed (beginning in the spring of 2022 and finishing in 2023]. These elements have been prioritized as the locations with the most immediate benefit to the public. The project elements not delivered within this phase will be funded through additional impact fees, grants, and other local funding sources. Additional details are available on the BUILD website.

September 12, 2022

The week of September 12 through September 16, crews remain present throughout the Mullan area. Thank you for your continued patience. 

 

REMINDERS:

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

Please plan ahead and avoid left turns from Flynn Lane onto Mullan Road. We encourage you to use Mary Jane Boulevard and Broadway, Flynn Lane and Broadway or England and Reserve to head east.

 

CONSTRUCTION UPDATE 

Various traffic changes are taking place in the coming weeks. These locations are bolded below.

 

Major roadwork has wrapped up at the north end of Mary Jane Boulevard. Striping will be taking place this week. Please be mindful of cars parked on Mary Jane Boulevard and signs to indicate when stripe painting is scheduled. 

 

Connected to this, but part of a different MDT project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This MDT project also includes improvements to the Flynn Lane/Broadway intersection. Traffic detours will be present in the coming weeks as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  Please anticipate delays.

 

In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. This detour will be shifted on Monday, September 19. Here, crews are continuing paving of the roundabout and utility work at the intersection of Mary Jane Boulevard and Mullan Road. 

 

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly constructed frontage road. Here, crews are working to place gravel for the roundabout in this location.

 

Starting Monday, September 19, a closure will be present at the intersection of England Boulevard and Flynn Lane. Detour signs will direct traffic around the intersection closure. The closure will take place for 3 – 5 days as water main work is completed. A photo of the closure and detour route is below.

Similar to past weeks, utility and water work is taking place on England Boulevard between Flynn Lane and George Elmer Drive.

 

Please prepare for 10-20 minutes of delays when traveling through any of the above work zones. 

 

Mark your calendars: A second construction open house is scheduled on Tuesday, September 27 from 4:30pm – 6:30pm at the Hellgate Elementary School Cafeteria in Building 3. The project team will be present to answer questions. No formal presentation will be made. Please join us to ask questions and learn more.

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

September 6, 2022

The week of September 6 through September 9, crews remain present throughout the Mullan area. Construction will not take place on Monday, September 5 for Labor Day.

 

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe.

 

School is in session! Please be mindful of traffic, bicyclists and children in the area.

 

---

 

Roadwork continues on the north end of Mary Jane Boulevard. Specifically, paving is wrapping up between Flynn Lane and Broadway. 

 

Connected to this, but part of a different MDT project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This MDT project also includes improvements to the Flynn Lane/Broadway intersection. Traffic detours will be present in the coming weeks as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  Please anticipate delays.

 

In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. Here, crews are continuing paving and utility work for the roundabout at the intersection of Mary Jane Boulevard and Mullan Road. This week, crews are working on the roundabout truck apron, approach preparation, and concrete pours.

 

George Elmer Drive between Mullan Road and Bell Tower Road remains closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly constructed frontage road. Here, crews are working to excavate the roundabout in this location.

 

Next week, a closure will be present at the intersection of England Boulevard and Flynn Lane. Detour signs will direct traffic to alternate routes. The closure will take place for a few weeks as water main work is completed.

 

Similar to past weeks, utility work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. 

 

Please prepare for 10 - 20 minute delays when traveling through any of the above work zones. 

 

An updated project timeline is posted on the BUILD webpage linked here: https://www.mullanbuild.com/schedule.

 

Mark your calendars: A second construction open house is scheduled on Tuesday, September 27 from 4:30pm – 6:30pm at the Hellgate Elementary School Cafeteria in Building 3. The project team will be present to answer questions. Details to come as the date approaches!

 

Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

 

Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com

 

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

August 29, 2022

The week of August 29 through September 2, crews remain present throughout the Mullan area.


PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for traffic violations in the work zone. Thank you for your understanding as we work to keep everyone safe!


School starts for Hellgate School District on Wednesday, August 31. Please be aware of increased traffic and pedestrians and continue to be cautious when driving, walking, or bicycling. 


Roadwork is taking place on the north end of Mary Jane Boulevard. Specifically, paving continues between Flynn Lane and Broadway. Access to Broadway from Veterans Way and Summit Beverage continues to be redirected through Flynn Lane.


Connected to this, but part of a different MDT project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This MDT project also includes improvements to the Flynn Lane/Broadway intersection. Traffic detours will be present in the coming weeks as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  Please anticipate delays.


In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. Here, crews are continuing paving and utility work for the roundabout at the intersection of Mary Jane Boulevard and Mullan Road. A progress photo is included below.

Mullan Construction.jpg

George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of construction season for roundabout installation. Traffic continues to be detoured. Drivers are directed through the detour on Mullan Road via the newly construction frontage road. 


Lastly, utility work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. 


Please prepare for 10 - 20 minute delays when traveling through any of the above work zones. 


An updated project timeline is posted on the BUILD webpage, linked here.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

August 22, 2022

The week of August 22 through August 26, crews remain present throughout the Mullan area.


PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD. Highway patrol crew members are present. Fines double for drivers receiving speeding tickets in the area. Thank you for your understanding as we work to keep everyone safe!


School starts for Hellgate Elementary School District on Wednesday, August 31. Please be aware of increased traffic and pedestrians and continue to be cautious when driving, walking or bicycling. 


Roadwork is taking place on the north end of Mary Jane Boulevard. Specifically, paving continues between Flynn Lane and Broadway. On Monday, access to Broadway from Veterans Way and Summit Beverage will be redirected through Flynn Lane.


Connected to this, but part of a different MDT project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This MDT project also includes improvements to the Flynn Lane/Broadway intersection. Traffic detours will be present in the coming weeks as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  Please anticipate delays.


In addition, a detour remains on Mullan Road, located immediately east of Flynn Lane. Here, crews continue paving the roundabout at the intersection of Mary Jane Boulevard and Mullan Road.


George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of construction season for installation of the roundabout. Traffic continues to be detoured. The detour on Mullan Road will be moved to a newly constructed frontage road after it has been paved.  This frontage road paving is currently planned for Tuesday, August 23. Drivers will notice a new traffic configuration. 


Lastly, utility work is taking place on England Boulevard between Flynn Lane and George Elmer Drive. 


Please prepare for 10 - 20 minutes of delays when traveling through any of the above work zones. 


An updated project timeline is posted on the BUILD webpage, linked here.

August 15, 2022

The week of August 15 through August 19, crews remain present throughout the Mullan area.


PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD.


As a reminder, school starts for Missoula County Public Schools on Wednesday, August 31. Please be aware of increased traffic and pedestrians and continue to be cautious throughout the area.


Roadwork is taking place on the north end of Mary Jane Boulevard. Specifically, paving continues between Veterans Way, Flynn Lane, and up to Broadway. 


Connected to this, but part of a different MDT project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This project also includes improvements to the Flynn Lane/Broadway intersection. Traffic detours will be present in the coming weeks as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  Please anticipate delays.


In addition, a detour remains on Mullan Road located immediately east of Flynn Lane. Here, crews are continuing the construction of the roundabout at the intersection of Mary Jane Boulevard and Mullan Road. 


Similar to past weeks, George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of the construction season for the installation of a roundabout. Traffic continues to be detoured.


This week, a detour on Mullan Road will be opened and traffic will be shifted to the detour as crews begin constructing the roundabout at the intersection of George Elmer and Mullan Road. Drivers can anticipate shifting to the detour starting mid-week.


Lastly, utility work is taking place on both sides of England Boulevard between Flynn Lane and George Elmer. 


Please prepare for 10 - 20 minutes of delays when traveling through any of the above work zones. 

August 8, 2022

PLEASE WATCH FOR SIGNS AND SLOW DOWN ON MULLAN ROAD.


The week of August 8 through August 15, paving and utility work is taking place between Broadway and Veterans Way. This work is associated with the Mullan BUILD Project. Connected to this, but part of a different project, crews are starting the installation of a signalized intersection where Mary Jane Boulevard connects to Broadway. This project also includes improvements to Flynn Lane/Broadway intersection. Traffic detours will be present as Flynn Lane and Mary Jane Boulevard will be partially closed for periods of time to facilitate the construction.  


A detour remains on Mullan Road located immediately east of Flynn Lane. Here, crews are working to level material in the area in preparation for the roundabout that will soon connect to Mary Jane Boulevard. 


Similar to past weeks, George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of construction season. Traffic continues to be detoured. Please watch for signs.


Lastly, utility work is taking place on both sides of England Boulevard. 


Please prepare for 10 - 20 minutes of delays when traveling through any of the above work zones. 


Thank you for your patience. Please slow-down in the area and continue to pay attention to other cars, equipment, signs and crews!

August 1, 2022

Thank you for your patience and understanding as active construction continues in the Mullan area.


The week of August 1 through August 8, crews remain in similar locations to last week.


Roadwork is taking place on the north end of Mary Jane Boulevard. Specifically, paving is occurring between Veterans Way and Flynn Lane. As new asphalt is placed, barricades will be located to keep traffic off of the fresh asphalt. Please stay off the roadway where specified.


A detour remains on Mullan Road for the Mary Jane Boulevard roundabout in this location.  Gravel placement is taking place in preparation for paving.


In addition, George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of the summer. Traffic will be detoured, and drivers should expect delays. 


Utility work and topsoil removal is also beginning on England Boulevard. 


Please prepare for 5-10 minutes of delays when traveling through any of the above work zones. 

July 25, 2022

Roadwork continues on the Mullan BUILD project. Please remember to SLOW DOWN and be mindful of other cars, signage, crews and equipment when entering a work zone. 


The week of July 25 through August 1, drivers will notice utility work continuing on Mullan Road for the Mary Jane Boulevard roundabout in this location. A detour remains here. Soon, gravel placement will take place in preparation for paving.


Crews are also present at the north end of Mary Jane Boulevard for the connection through to Broadway. Paving will take place this week and Flynn Lane will be limited to one lane during paving operations. Crew members will be present to direct traffic.


Lastly, roadwork is taking place on the south and north end of George Elmer Drive. The north end of George Elmer Drive between Mullan Road and Bell Tower Road is closed through the end of the summer. Traffic will be detoured, and drivers should expect delays. 


Please prepare for 5-10 minutes of delays when traveling through any of the above work zones. Thank you for your patience and understanding. Our team’s number one priority is safety.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

July 18, 2022

The week of July 18 through July 25, drivers can continue to expect a detour on Mullan Road in preparation for the Mary Jane Boulevard and Mullan roundabout. This week, crews will be leveling the area with dirt. Traffic will be impacted. Please expect delays.


Kiewit and consultants are also present at the north end of Mary Jane Boulevard near Flynn Lane and Veterans Way. This location will be prepped for paving. No impacts to traffic are taking place.


Lastly, travelers will notice crews and equipment on the north and south portions of George Elmer Drive. The north end of George Elmer Drive between Mullan Road and Bell Tower Road will be closed beginning Wednesday, July 20, in preparation for the roundabout at George Elmer Drive and Mullan. Traffic will be detoured to alternate routes, and drivers should expect delays. 


Thank you for continuing to watch for signs, other drivers, equipment, and crews when traveling through the work zones.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

July 11, 2022

The week of July 11 through July 18, drivers can continue to expect a detour on Mullan Road in preparation for the Mary Jane Boulevard and Mullan roundabout. Crews are currently completing utility work in this area.


Crews will be present in the area Monday through Saturday for the duration of construction.


Kiewit and consultants will also be working at the north end of Mary Jane Boulevard near Flynn Lane and Veterans Way. This will soon be paved in preparation for a connection from Flynn Lane through to Broadway.


Please anticipate a few minutes of delay when traveling through work zones. Watch for signs, other drivers, equipment, and crews.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

July 5, 2022

The week of July 5 through July 11 drivers can expect a detour on Mullan Road. This detour will remain until crews complete work on the roundabout at Mary Jane Boulevard and Mullan. 


In addition, work continues at the north end of Mary Jane Boulevard near Flynn Lane and Veterans Way. This area will soon be paved in preparation for a connection from Mary Jane Boulevard through to Broadway. Drivers will be directed via lights on Flynn Lane as crews work their way through Mary Jane Boulevard.


Safety is the number one priority of the project team and construction crew. Please be mindful of other cars, workers and equipment and slow down when entering the work zone.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage: www.mullanbuild.com


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

June 27, 2022

The week of June 27 through July 3, drivers can expect the north shoulder of Mullan Road between Dublin Street and Flynn Lane to be closed. This shoulder closure is allowing crews to construct a temporary detour for the roundabout going in on the south end of Mary Jane Boulevard on Mullan. The speed limit will be reduced and may cause a few minutes of delay. Both lanes of traffic will be open.


Crews will not be working on Monday, July 4.


After the fourth of July holiday, a detour will be present on the south side of Mullan Road across from Mary Jane Boulevard. Drivers will be directed through the detour. 


Questions on the roundabout design? Roundabouts are relatively new to Montanans and it’s understandable that neighbors may have questions or concerns about this design selection.


Roundabouts are proven safety measures as they significantly reduce crashes that result in serious injury or death. Roundabouts promote lower speeds, reduce conflict points for drivers and are designed to efficiently move traffic and function well for trucks and very large vehicles. For more information on how to drive a roundabout, follow this link.

June 20, 2022

The week of June 20 through June 27, crews will be working near Camden Street and Flynn Lane and are headed towards Veterans Way. This work is in preparation for the extension of Mary Jane Boulevard to Broadway.


Depending on favorable weather, on June 27, drivers can expect the south shoulder of Mullan Road between Dublin Street and Flynn Lane to be closed. This shoulder closure will be present as crews build a temporary detour for the roundabout. The speed limit will be reduced and may cause a few minutes of delay. Both lanes of traffic will be open.


Details will be provided on the detour as the end of June approaches.


Please slow down in the work zone and watch for other vehicles, pedestrians, crew members and posted signage. 

June 13, 2022

The week of June 13 through June 20, drivers can continue to expect delays when traveling through the Mullan BUILD project area. Please slow down and watch for other drivers, equipment and crew members. 


Construction crews are completing work off the roadway on the south end of George Elmer Drive. This will have no impact to traffic.


Meanwhile, drivers and residents will also notice crews placing gravel north of Mary Jane Boulevard. This is the groundwork for the connection between Mary Jane Boulevard through to Broadway Street.


Thank you for your patience as roadwork continues.

June 6, 2022

The week of June 6 through June 13, drivers can expect a few minutes of driving delays throughout the Mullan BUILD project area. Kiewit construction crews are continuing earthwork operations and will begin sewer utilities on the south end of Mary Jane in preparation for the roundabout. 


In addition, crews will be present at Camden Street/ Flynn Lane and at the north end of George Elmer Drive. 


Meanwhile, the City of Missoula is beginning widening work on Mullan Road at the future intersection of Chuck Wagon Drive. Please visit this webpage for more information.


Please continue to slow down in the work zone, watch for other drivers, equipment and crew members.

May 30, 2022

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


Crews will not be present on Monday, May 30 for the Memorial Day holiday.


The week of May 31 through June 6, drivers can expect limited delays. Kiewit Construction crews continue to work on the north end of Mary Jane Boulevard. Utility work is also occurring on the southern portion of Mary Jane Boulevard and the northern section of George Elmer Drive. 


Signs will be posted to slow down throughout the area however, traffic control will be limited, and drivers should not anticipate delays.


Thank you to all those who attended the open house at Hellgate Elementary on Thursday, May 26. The project team will hold another public event later this summer.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

May 2022 Update: Open House

In partnership with the City of Missoula, Missoula County invites neighbors and interested parties to attend a Mullan BUILD project open house event on Thursday, May 26, from 4 – 6 pm at the Hellgate Elementary cafeteria in building three on Flynn Lane. 

Now that construction has started, the BUILD project team welcomes community members to ask questions and review the project's design plans during this event. The open house will allow the public to review maps one-on-one with team members and ask specific questions about their property and the overall construction schedule. 


Kiewit Corporation, the project’s contractor, has started utility and road work in the Mary Jane North and Broadway area and on George Elmer Drive. Neighbors have likely already experienced traffic control and delays throughout the region. The project team hopes to answer questions, provide resources, and discuss what folks can anticipate with upcoming construction during this open house.


There will be no formal presentation.


For more information:

Please email becca@bigskypublicrelations.com with questions.

May 16, 2022


Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


The week of May 16 through May 23, construction continues in the Mullan area. A closure of George Elmer Drive will occur May 17 – May 19 on the south end of this street near its intersection with Mullan Road. A detour will be put in place via Roundup Drive. Travelers will notice detour signs to direct traffic flow. Please prepare for delays when traveling this route. 

 

A public meeting is being held on Thursday, May 26 from 4-6pm at the Hellgate Elementary Cafeteria in Building 3 on Flynn Lane. All are welcome to pop-in anytime to ask the project team questions. No formal presentation will be made.


Be mindful of workers, equipment and other drivers when traveling through the area.

May 9, 2022

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


For the week of May 9 to May 16, drivers can continue to anticipate sewer utility work on Mary Jane Boulevard, Flynn Lane and Broadway in preparation for the road connection to Broadway.  


Crews are also present on the south end of George Elmer Drive. A closure will occur May 17 – May 19 on the south end of George Elmer Drive near the 44 Ranch Subdivision. A detour will be put in place via Roundup Drive. Travelers will notice signs to direct traffic flow. Please prepare for delays when traveling this route. 


Slow down, watch for signs, equipment and crew members throughout the area.

May 2, 2022

Good morning,

  

Missoula County, the City of Missoula, and contractors have partnered with Kiewit Construction to complete the Mullan BUILD project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


For the week of May 2 to May 9, the southern access near Summit Beverage on Flynn Lane will continue to be closed. A shoofly (a temporary detour that carries traffic around roadwork) on the north end of Flynn Lane will remain to detour drivers around active sewer and utility work.


In the coming weeks, crews will be present on the south end of George Elmer Drive. Be mindful of signs and slow down throughout the Mullan area. 


In mid-May, a closure will occur for three days on the south end of George Elmer Drive near the 44 Ranch Subdivision. A detour will be put in place. Please prepare for delays when traveling this route.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage linked here


Take care,

Becca MacLean, on behalf of the BUILD Project Team

April 22, 2022

Missoula County, the City of Missoula and contractors have partnered with Kiewit Construction to complete the Mullan BUILD Project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).

  Good afternoon,

  

Missoula County, the City of Missoula and contractors have partnered with Kiewit Construction to complete the Mullan BUILD Project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


For the week of April 25 to May 2, Kiewit will be closing the southern access near Summit Beverage on Flynn Lane. A shoofly (a temporary detour that carries traffic around roadwork) on the north end of Flynn Lane will detour drivers around active sewer utility work. When traveling through the work zone travelers can anticipate flaggers directing traffic and 5 – 10 minutes of delay. In the coming weeks, please anticipate work occurring on the south end of George Elmer. Be mindful of signs and slow down throughout the Mullan area. 


On Thursday, April 21, a groundbreaking ceremony was held to officially kick off the project and thank project partners. For details, please read coverage by the Missoulian or KPAX.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage linked here


Take care,

Becca MacLean, on behalf of the BUILD Project Team


Construction.jpg

April 18, 2022

Missoula County, the City of Missoula and contractors have partnered with Kiewit Construction to complete the Mullan BUILD Project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


For the week of April 18 to April 25, Kiewit will continue utility work along the north end of Mary Jane Boulevard. Traffic control including flaggers will be set directing cars from one lane to another in the coming weeks as crews work in this area. A detour will be added as crews move to complete utility work on the south end of Mary Jane Boulevard. Drivers should expect a few minutes of delay at this time. 

April 13, 2022

The BUILD project team will regularly provide construction updates via email and on the BUILD project web page. Please send neighbors and all interested parties my way to receive updates! Our goal is to inform you of what to anticipate in your neighborhood throughout construction.


Missoula County, the City of Missoula and contractors have partnered with Kiewit Construction to complete the Mullan BUILD Project, which is anticipated to be substantially completed by the end of 2022. The work includes infrastructure and roadway construction of Mary Jane Boulevard South, Mary Jane Boulevard North, England Boulevard, George Elmer Drive, and two roundabout intersections along Mullan Road (Mullan/George Elmer Drive and Mullan/Mary Jane Boulevard).


For the week of April 13 to April 20, Kiewit Corporation, the project contractor, is completing potholing and utility work before diving into full construction.  Drivers and pedestrians can expect to see crews and equipment completing potholing fills on Mary Jane Boulevard South and North. This includes the use of flaggers to direct traffic. Please anticipate minor to no delays.


Please feel welcome to email me at becca@bigskypublicrelations.com with any questions or feedback.

March 2022

Missoula County, in partnership with the City of Missoula, announces that construction on the Mullan BUILD project will begin next month. 

Missoula County officials received final approvals from the Federal Highway Administration this week.

Kiewit Corporation, the project’s contractor, will begin roadwork at the Mary Jane North and Broadway area in early April. Drivers will also notice utility and shoulder work beginning along Mullan Road. Complete road construction will take place this summer and early fall. In 2022, Missoulians can anticipate construction occurring on Mary Jane Boulevard, George Elmer South and England Boulevard, as these are the initial priorities of the project. Drivers can anticipate delays of up to 10 -15 minutes when traveling throughout the project area from April to October. Updates will be provided regularly on construction progress and anticipated delays. 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with $8 million of local funding from the City and County, will support the first phase of Mullan BUILD project construction. The BUILD project will ultimately play an integral role in how Missoula will grow. A network of streets will be built to improve connectivity and provide access to current and future homes and businesses.

For more information:

Please email becca@bigskypublicrelations.com with questions.

July 30, 2021

In case you missed the previous update, Missoula County, in partnership with the City of Missoula, announced a Mullan BUILD project schedule change. Initial construction was slated to begin later this summer and now has been pushed to the spring of 2022 due to unforeseen funding challenges. 

Limited availability of materials and labor have led to cost inflation in current bid prices. The Mullan BUILD team has continued communication with contractors, re-analyzed costs, tried to find flexibility in the schedule and made every effort to move forward with construction this year. The project plan prioritized elements of the project (Mary Jane Boulevard, George Elmer South, England Boulevard) and scenarios for future funding remain the same. The only change is the timeframe of initial construction shifting from 2021 to 2022. The team anticipates being able to complete the majority of the construction by the end of 2022 if available funding, and project budgets align. 

With this information in mind, the BUILD team is currently working to acquire additional funding, finalize Federal BUILD grant agreement steps, and continue conversations regarding right of way and development efforts in the area.

In the coming months, updates will be fairly quiet unless there is significant new information to announce. We will inform all stakeholders as progress is made. We anticipate more significant updates towards the beginning of fall and early winter.

In the meantime, please feel welcome to email takami@bigskypublicrelations.com with any questions or feedback.

Additional project resources are available on the Mullan BUILD webpage linked here

Take care,

Becca MacLean on behalf of the BUILD Project Team

June 18, 2021

Happy June! We hope you are enjoying the beginning of summer. Please see below for important updates on the BUILD project. 

Missoula County, in partnership with the City of Missoula, announce a Mullan BUILD project schedule change. Initial construction was slated to begin later this summer and now has been pushed to the spring of 2022 due to unforeseen funding challenges. 

Limited availability of materials and labor have led to significant cost inflation in current bid prices. Current project costs exceeded available funding, forcing the team to re-evaluate the project schedule. The additional time will allow the Mullan BUILD team to seek additional local funding, further analyze material costs and move forward with the official grant agreement for the BUILD funding.


Throughout this process, the Mullan BUILD team has been in communication with contractors, re-analyzed costs, tried to find flexibility in the schedule and made every effort to move forward with construction this year. The project plan, prioritized elements of the project and scenarios for future funding remain the same. The only change in the timeframe is initial construction moving from 2021 to 2022. With better prices in the spring, the team anticipates being able to complete the majority of the construction by the end of 2022. 

Missoula County received a $13 million federal BUILD grant to construct a new infrastructure network in the Mullan Road area. The federal grant, coupled with local funding from the City and County, will fund the first phase of the Mullan BUILD project. Project leads estimate that $40 million of funding is required to complete the entire project. Because of the large funding gap, future project phases will be constructed as additional funding becomes available. Prioritized elements of work to go in the 2022 construction season include Mary Jane Boulevard, George Elmer South and England Boulevard. Other projects, such as utility extensions and minor intersection improvements related to development, will still proceed in 2021 separate of the BUILD project.   


Please email Becca at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage linked here. This webpage will be updated to fully reflect the timeline update.

May 7, 2021

The Mullan BUILD team, including Missoula County, the City of Missoula and consultants, have completed the 100 percent design plans. These plans are linked on this webpage. Plans include intersection designs, landscaping, pavement marking, signing details and more. Now that design plans are complete, the BUILD team continues to finalize the acquisition of necessary right-of-way and seek additional funding for future phases of the entire project. 


Prioritized elements of the project, including portions of Mary Jane Boulevard South, Mary Jane Boulevard North, George Elmer South and England Boulevard, will go into construction scheduled to begin this summer. This initial construction phase will take place throughout 2021 and 2022. However, the timeframe is subject to change based on weather and contractor availability. Any schedule updates will be communicated moving forward as needed. 


As initial roadwork nears this summer, email updates will become more regular to ensure that residents are kept up to date. Please send neighbors or any interested parties our way if they would like to subscribe.


In addition to this, prior to and during construction season, opportunities will be available for the public to engage with the project team. The BUILD team encourages and values feedback and comments throughout the process seeing that much of the greater project is yet to be designed. 


Virtual Open House Resources:

Thank you again to all those who attended the virtual open house on Tuesday, April 6. If you missed it or would like to revisit materials, please see resources linked below.


Introductory session

Breakout Session A - Design Features 

Breakout Session B - Construction Impacts

Breakout Session C - Funding and Future Considerations


In addition, the recordings for all of the open house sessions are located at this link. We encourage you to revisit Breakout Session recordings that interest you.


Contact Us + Public Feedback

Please email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage linked here

April 15, 2021

Please see below for updates and reminders on the BUILD project. 


Virtual Open House Resources

Thank you to all those who attended the virtual open house on Tuesday, April 6. The BUILD project team appreciated the productive questions and feedback they received. We are grateful for your time!


If you missed the open house or would like to revisit materials, the PDFs for all of the presentation slide decks are linked below:


Introductory session

Breakout Session A - Design Features 

Breakout Session B - Construction Impacts

Breakout Session C - Funding and Future Considerations


In addition, the recordings for all of the open house sessions are located at this link. We encourage you to revisit Breakout Session recordings that interest you.


Mullan BUILD Project Update

As mentioned in previous weeks, the BUILD team, including Missoula County, the City of Missoula and consultants are in the final stages of the 100 percent design. In addition to this, the team is focused on BUILD grant agreements, acquiring needed right-of-way and seeking additional funding for future phases of the entire project. 


The team is moving towards construction scheduled to begin early summer 2021. This initial construction phase will take place throughout 2021 and 2022. However, this timeframe is subject to change and schedule updates will be communicated moving forward, as needed. 


Contact Us + Public Feedback

Please email me at becca@bigskypublicrelations.com with any questions or feedback.


Additional project resources are available on the Mullan BUILD webpage linked here

March 26, 2021

Virtual Open House: APRIL 6

You are invited to a virtual open house on Tuesday, April 6 at 11:30 a.m.


Registration is required, and you may register for this event using this link. This virtual meeting will be held via Microsoft Teams and will include an initial presentation as well as three breakout sessions. The initial presentation will include introductions, background information on the BUILD project, an overview of breakout session content, and more.


Immediately following the initial virtual meeting, three breakout sessions will take place via Microsoft Teams. The dial-in information will be provided to all registered participants. These sessions will be held on three topics including (a) design features (roundabouts, parking concerns, etc.), (b) construction schedule (anticipated impacts, construction priorities, etc.), and (c) funding + future priorities (impact fees, future funding, etc.) 


Each session will be attended by category experts to answer questions. These breakout sessions will function as open discussions and not presentations. Every attendee is welcome to join any breakout session any time (bouncing between all three is encouraged). Please let me know if you have any questions.


Mullan BUILD Project Update

The BUILD team, including Missoula County, the City of Missoula and consultants are in the final stages of the 100 percent design. In addition, the team is focused on BUILD grant agreements, acquiring needed right-of-way and seeking additional funding for future phases of the entire project. 


To restate, construction is tentatively scheduled to begin early summer 2021. This initial construction phase will take place throughout 2021 and 2022. However, this timeframe is subject to change and schedule updates will be communicated moving forward, as needed.

March 5, 2021

Mullan BUILD Project Update

As a reminder, the Mullan BUILD team has completed the 90 percent project design plans which you can view on the webpage at this link. Please note, these plans are comprised of the project’s prioritized elements including portions where construction is deferred to subsequent phases of the project once additional funding is acquired. 


In addition to finalizing design plans to the 100 percent level, the team is currently focused on BUILD grant agreements, acquiring needed right-of-way and seeking additional funding for future phases of the entire project. 

Construction is tentatively scheduled to begin early summer 2021. This 


initial construction phase will take place throughout 2021 and 2022. However, this timeframe is subject to change and schedule updates will be communicated moving forward.


Impact Fee Funding

Impact fees will continue to supplement funding for the remainder of the BUILD project. As of March 2, 2021, the City of Missoula City Council has approved the use of impact fees on new developments in the greater Mullan area. The addition of these fees will allow for more elements of the BUILD project to be completed in the coming years. Now that the ordinance has been adopted, fees will go into effect on March 31, 2021. For more detailed information please visit the Engage Missoula webpage. Updates to come on impact fees specific to the BUILD project as the year progresses.


Open House

As a reminder, you are invited to a virtual open house on Tuesday, April 6 at 11:30 a.m. Register for this event at this link. This virtual meeting will be held via Microsoft Teams and will include a presentation as well as the opportunity to chat with project team members in smaller groups about specific topics of interest. More details to come as the date approaches. 


Contact Us + Public Feedback

Please reach out with questions or feedback to becca@bigskypublicrelations.com or call 406-207-4484. 


As a reminder, if you are interested, we welcome you to peruse the Mullan BUILD webpage linked here. Here, you will find environmental documentation, recordings of past public meetings, the overall project schedule, and more. Your feedback, questions and comments are encouraged on all elements of the project.

February 5, 2021

Mullan BUILD Project Update:

As a reminder, the Mullan BUILD team has completed the 90 percent design plans for the project.  These plans are available on the BUILD webpage at this link. These designs include specific intersection details, irrigation elements, drainage landscaping, lighting and electrical work, and much more. However, please note, these plans include designs for the prioritized elements of the project, inclusive of portions where construction is deferred to subsequent phases of the project once additional funding is acquired. 


After this 90% package is approved by the BUILD project team, which includes experts from the City of Missoula and Missoula County, DJ&A Engineering will be focused on a 100% design plan. Throughout all of these steps, the project team has been focused on prioritizing specific areas of work (Mary Jane Boulevard South, Mary Jane Boulevard North, George Elmer South, England Boulevard) to fit within current project funding confines provided by the BUILD grant. In addition to design plans, the team will be focused on finalizing BUILD grant agreements, acquiring needed right-of-way and seeking additional funding for future phases of the larger project. 


Construction is tentatively scheduled to begin late-spring 2021. This initial construction phase will take place over 2021 and 2022. The timeframe is subject to change.


To provide background, the Mullan BUILD team, inclusive of DJ&A Engineering, City of Missoula and Missoula County representatives, and more, initially applied for BUILD grant funding and received $13 million in total. This required a prioritization of specific project elements in order to move forward with the limited funding. Project element prioritizations listed above will be completed in this initial phase of work (2021, 2022), dates subject to change. As additional funding is acquired via impact fees or grant funding, the entire project throughout the Mullan area can be delivered. 


Seeking Additional Funding:

As described above, impact fees are being considered as a potential avenue for funding the reminder of the BUILD project. Throughout February and early March, the City of Missoula is presenting plans to City Council via a Public Hearing scheduled for February 22. Additional discussion dates and information is posted on the City website linked here as well as on our BUILD webpage linked here. Details to come as the month progresses.


Open House: 

All are invited to a virtual open house on Tuesday, April 6 at 11:30 a.m. Register for this event at this link.


We hope you can join us for a presentation and question-and-answer session with the project team prior to construction!


Contact Us + Public Feedback:

Please reach out with questions or feedback to becca@bigskypublicrelations.com or call 406-207-4484. We will provide additional updates as construction nears.


As a reminder, if you are interested, we welcome you to peruse the Mullan BUILD webpage linked here. Here, you will find environmental documentation, recordings of past public meetings, the overall project schedule, and more. Your feedback, questions and comments are encouraged on all elements of the project.

January 19, 2021

Mullan BUILD Project Update:

The Mullan BUILD team has completed the 90 percent design plans for the project. They have more accurately determined costs and additional factors when narrowing project locations advancing to construction this year with the available funding. Additionally, the BUILD team is continuing to work towards the completion of all the right-of-way necessary for project elements that may not be constructed with the first round of funding.


As many understand, this project is being completed with limited funding through the BUILD grant. This includes work on Mary Jane Boulevard South, Mary Jane Boulevard North, George Elmer Drive South, and England Boulevard. This work will take place tentatively in 2021 and 2022 as the initial phase of the project.


The team’s goal is to complete all project elements and identified improvements in addition to the prioritizations listed above including Grant Creek restoration, Tipperary Way Trail, etc. The plan is to complete the entire project scope once additional funding and right of way is acquired.  More updates to come.


Please note, the tentative schedule for select road and subsurface construction will begin late-spring 2021. Initial construction will take place over both 2021 and 2022 and is anticipated to be substantially completed by November 2022. The most significant construction will occur in 2022. To reiterate, this timeframe is for the first phase of work within the current funding confines. However, the schedule and time frame are subject to change. 


Open House: 

The media and public are invited to a virtual open house in early April. Registration and details for this event will be located at this link. More information to come.


This open house will be structured similarly to past public meetings. There will be a brief presentation covering project design plans, parking, lighting, the construction schedule and general elements to be aware of. Then, the project team will conclude with a question-and-answer session to make sure that all attendee questions and concerns are addressed prior to 2021 construction beginning. 


Contact Us + Public Feedback:

Please reach out with questions or feedback to becca@bigskypublicrelations.com


As a reminder, we invite you to peruse the Mullan BUILD webpage linked here. Here, you will find recordings from past public meetings, extensive environmental documentation, the overall project schedule, and more. The BUILD project team welcomes feedback, questions and comments on all elements of the project.